It’s been a good year to work on the North Slope.
According to new data from the federal government, December’s employment estimate was 323,900, up 1,500 from 322,400 in December 2024, with 51,400 of those jobs in oil and gas, construction and transportation – all fueled by North Slope activity.
Some highlights:
- Oil and gas jobs were estimated at 9,300, up from 8,700 in December 2024.
- Construction was 18,100 this past December, down slightly from 18,500 in December 2024.
- Retail was down in December, at 34,300 against 34,900 in December 2024.
- Transportation was 24,000 in December, up from 23,000 in December 2024.
Construction in 2026, led by oil and gas, will be level with 2025, according to a study commissioned by the Associated General Contractors Alaska (AGC) chapter. AGC releases its annual report in early spring. It is essentially a survey of opinions among contractors combined with information from other sources. McKinley Research Group compiles the reports.
The bottom line is that total construction spending appears level between 2025 and 2026 but with private sector contracting up and public sector work down, writes Tim Bradner in his latest issue of Alaska Economic Report. Total spending is estimated at $6.71 billion for the year, with $3.765 billion from private companies and $2.945 billion through federal, state and municipal agencies.
A few highlights:
- Oil & gas: $1.4 billion
- Airports/ports/rail: $900 million
- Utilities: $755 million
- Highways/roads: $690 million
- Residential: $430 million
- Health care: $280 million
- Mining: $190 million
The survey notes that oil and gas construction will decline with completion of the new Pikka field, but other projects will continue. ConocoPhillips, meanwhile, has 3,000 at work on its Willow project, now about 50% complete.
“For construction, the elephant in the room is of course the Alaska LNG Project. Glenfarne, the energy company that is now the state’s partner in this, feels it can get investors this year for a phase one of the project, the 42-inch pipeline from the North Slope to Southcentral Alaska that would serve Alaska markets,” Bradner writes. “The latest is that an investment approval for the pipeline could come in March. Phase two of the project is a large natural gas liquefaction plant planned at Nikiski, on the Kenai Peninsula. When the LNG plant is built the project can fully ramp up to serve export customers.
“But the project faces headwinds, so nothing is certain. Glenfarne has been busy this winter negotiating contracts with Alaska companies and contracts with suppliers for pipe and other materials. These can’t be finalized until the investors are secured and a Final Investment Decision is made. But if, and when, all that happens, having the contracts and procurement agreements, even if provisional for now, will save a lot of time.”
... See MoreSee Less
Tucked into the west side of the North Slope just a handful of miles from ANWR, a rig is preparing to drill a $180 million well at Point Thomson, a large gas and condensate field.
It is the first new well drilled at Point Thomson since 2016 and logistics are a major part of what makes it so expensive, operator Hilcorp said.
Doyon Drilling’s Rig 15, previously on Spy Island in the Nikaitchuq field, northwest of Kuparuk, was barged to the remote site, which is only accessible by air year-round, sea during the summer and a new, 60-mile ice road built this winter. The price tag: $40 million.
Point Thomson is now producing about 4,000 barrels per day of condensate, a volatile hydrocarbon liquid that condenses from "wet" natural gas as the pressure drops. Production has been way shy of its 10,000 barrels per day goal because of technical challenges in producing and injecting produced gas back into the high-pressure reservoir at the field, Tim Bradner writes in the latest edition of Alaska Resource Review.
The new well is expected to bring production to the target of 10,000 barrels/day when completed in the second half of 2026. The Point Thomson asset also includes a 22-mile pipeline that connects the field with the 25-mile Badami pipeline at the small Badami oil field at essentially the halfway point between Point Thomson and the Trans Alaska Pipeline System.
“Hilcorp’s acquisition of BP’s Alaska assets included its share of Point Thomson. ExxonMobil was previously the Point Thomson field operator but has passed that responsibility to Hilcorp, which is known for its ability to improve the value of producing assets through efficiency and investment,” Bradner writes.
Point Thomson has an estimated 8 trillion cubic feet of natural gas as well as several hundred million barrels of the liquid condensates now being produced.
The gas reserves at Point Thomson are a major part of the confirmed 35 trillion cubic feet of reserves on the North Slope that could support the proposed large Alaska LNG Project. Prudhoe Bay holds the remaining confirmed gas reserves on the Slope.
More here. online.flippingbook.com/view/696133712/18-19/
Photo credit to Exxon Mobil
... See MoreSee Less
“Hilcorp is doing what it does best on the North Slope, investing aggressively and applying new technologies in mature oil and gas fields to boost production, in this case 48-year-old Prudhoe Bay,” writes veteran reporter Tim Bradner in the latest issue of Alaska Resource Review.
Hilcorp is taking lessons learned from Milne Point and applying them to the west end of Prudhoe, said Daniel Donovan, Hilcorp’s Western North Slope Asset Team Leader. Hilcorp calls the project “Taiga”, and it includes the development of two new pads targeted to develop the area’s huge viscous oil deposits, Donovan said.
Phase one — projected to deliver peak production of 25,000 barrels per day — centers on construction of the new “Omega Pad” drill site and 51 development wells, with first oil expected in 2028, Donovan said. A second phase would add “I-Pad,” at a nearby site, potentially bringing on an additional 15,000 barrels per day in the early 2030s.
“A substantial part of the reservoir to be tapped in the Prudhoe west end project is viscous oil similar to that in the Schrader Bluff viscous oil at Milne Point. Viscous oil is cooler than conventional crude oil mainly because it is typically found at shallower depths than the large conventional oil reservoirs on the North Slope, which are deeper and at warmer temperatures so that the oil flows more easily,” Bradner writes.
Since Hilcorp took over Milne, it has invested $2.5 billion over the past five years, built two new pads – Moose and Raven – and introduced a new polymer flood. The results have been phenomenal: production jumped from 17,000 barrels/day to more than 50,000, with the potential of 60,000 in the next few years. May the same approach work as well at Prudhoe.
Here’s the rest of the story. online.flippingbook.com/view/696133712/16-17/
... See MoreSee Less